On December 1, 2010, the Judicial Standards and Accountability Bill was introduced in the Lok Sabha.  The Bill revamps the present system of inquiry into complaints against judges.  The case of Justice Sen was the one of the more recent instances where the integrity of judges has been called into question.

A motion was moved by 58 members of the Rajya Sabha for the removal of Justice Soumitra Sen, (a Judge of the Calcutta High Court) on grounds of misappropriation of funds. The Chairman, Rajya Sabha constituted an Inquiry Committee on March 20, 2009 to look into the matter. The Committee comprising Hon’ble Justice B. Sudershan Reddy (Chairman), Hon’ble Justice T.S.Thakur and Shri Fali S. Nariman submitted its report on September 10, 2010.

Charges framed in the Motion

The two charges which led to an investigation into alleged misconduct of Justice Soumitra Sen were:

  • Misappropriation of large sums of money, which he had received in his capacity as Receiver appointed by the High Court of Calcutta; and
  • Misrepresentation of facts with regard to the misappropriation of money before the High Court of Calcutta

 

General observations of the Committee on the case:

  • Justice Sen’s assertion that he had the right to remain silent during the investigations was fallacious.
  • He did not cooperate with the Court proceedings; was not present for hearings, did not furnish information requested by the Court and did not provide any evidence in his defence.

 

Facts and Findings of the investigation by the Committee:

a. During the period he was an Advocate:

  • Justice Soumitra Sen was appointed Receiver in a case by an order of the Calcutta High Court on April 30, 1984. A Receiver appointed by the High Court has the power to collect outstanding debts and claims due in respect of certain goods.
  • As required by the High Court, the Receiver should file and submit for passing,     his half yearly accounts in the Office of the Registrar of the High Court. However, Justice Sen did not comply with this rule both as an Advocate and a Judge.
  • The High Court requires the Receiver to open only one account and not move funds without prior permission. However, the Committee found that two separate accounts were opened by Justice Soumitra Sen as Receiver, with ANZ Grindlays Bank and Allahabad Bank.
  • A total sum of Rs 33,22,800 was transferred in these accounts from the sale of proceeds of the goods which was not accounted for either when Justice Sen was an Advocate or when he was made a High Court Judge.
  • Justice Sen claimed he could not account for this amount since it was invested in a company called Lynx India Ltd. to earn interest. The Committee found this claim to be false as well.
  • The Committee concluded that this was a case of misappropriation of funds as both of the Receiver’s bank accounts were closed with a nil balance without any investments being made on behalf of the High Court.

b. During the period he was a Judge:

  • Justice Soumitra Sen was appointed a High Court Judge on December 3, 2003. The committee noted that Justice Sen’s actions were, “an attempt to cover up the large-scale defalcations of Receiver’s funds”.
  • After he became a Judge he did not seek any permission from the Court for approval of the dealings, as required by the Court, nor did he account for the funds.

Conclusion

Based on the findings on the two charges the Inquiry Committee was of the opinion that Justice Soumitra Sen of the Calcutta High Court is guilty of “misbehaviour”.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.